Verification

Verification of pile bearing capacity depends on the verification methodology selected in the "Piles" tab:

  • verification according to the factor of safety
  • verification according to the theory of limit states
  • verification according to EN 1997 (based on limit states approach)
  • analysis according to EA-Pfähle (based on the settlement analysis)
  • analysis according to SP 24.13330.2021 (the calculation follows exclusively the procedures described in SP 24.13330.2021 standard - no other safety factors are considered

Actual analyses (e.g. calculation of the pile base resistance) are the same for both options - they differ only by incorporation of design coefficients, combinations, and in the way of demonstrating the structure safety.

If the verification analysis according to CSN 73 1002 is selected, the verification is carried out exclusively according to the Commentary to CSN 73 1002.